Annex I

Infrastructural Projects Implemented or to be Implemented in 2009-2014 by Organizations under the Ministry Regional Development and Infrastructure of Georgia
N
Name of object/Project
Term of implementation
Work cost
Th. Laris
1.
Rehabilitation of internal streets of Akhalkalaki
2010
1,496.0
2.
Rehabilitation of local roads of Akhalkalaki
2009
1,309.0
3.
Rehabilitation of watering system of villages (Ikhtala-Aragva-Orja and Diliti-Vachiani) of Akhalkalaki Municipality
2009-2011
1,305.9
4.
Rehabilitation of streets of Ninotsminda
2009
652.3
5.
Construction of sewerage collectors and cleansing buildings in Ninotsminda
2009-2010
220.0
6.
Rehabilitation of watering and sewerage systems in Spandarian and Hovsepian streets of Ninotsminda
2010
300.8
7.
Works on building and repairing local administration buildings in village Poka
2011
190.4
8.
Rehabilitation of Spandarian street in Ninotsminda
2010
461.7
9
Works on Repairing of apartments of internally displaced persons in Gardabani
2009
988.6
10.
Works on Repairing of Dormitory in Gardabani
2009
99.2
11.
Works on Repairing of building of 121st professional technical school in Gardabani
2009
301.3
12.
Works on Repairing of apartments of internally displaced persons in former guard building in Gardabani
2009
199.8
13.
Rehabilitation of sewerage system of Gardabani district
2009-2010
535.5
14.
Works on gasification of apartments of internally displaced persons in Gardabani
2009
33.7
15.
Rehabilitation of watering system on territory of Marneuli Service Centre
2011-2012
4,078.9
16.
II water-pipe cell of Marneuli
2009
776.0
17.
Marneuli I - watering pipeline
2009
376.3
18.
Rehabilitation of internal roads of villages Tamarisi, Tsereteli and Saimerlo of Marneuli Municipality
2010
1,426.3
19.
Periodic repairing of Tbilisi-Tsiteli Khidi (Azerbaijani border) road
2008-2009
638.6
20.
Rehabilitation of Tbilisi-Kojori-Tsalka-Ninotsminda road
2008-2009
1,614.1
21.
Rehabilitation of Koda-Tetritskaro road
2008-2009
3,175.0
22.
Rehabilitation of Kveshi-Dzedzvnariani-Tandzia road
2009-2010
3,159.9
23.
Rehabilitation of Shulaveri-Tsiteli Khidi road
2009-2010
1,259.0
24.
Rehabilitation of Ponichala-Marneuli-Guguti (Armenian border) road
2009
1,719.7
25.
Rehabilitation of Marneuli-Tetritskaro-Tsalka road
2008-2009
2,651.4
26.
Rehabilitation of Didi Dmanisi-Dmanisi-Gomareti-Bediani road bridge
2009
73.7
27.
Rehabilitation of bridge of Bolnisi Sioni Monastery-Tsugrugasheni road
2010
184.0
28.
Rehabilitation of Didi Dmanisi-Dmanisi-Bediani road
2010-2011
4,994.0
29.
Rehabilitation of road and contiguous territory in village Mtisdziri in Gardabani Municipality
2010
233.9
30.
Prevention measures on 24th km of Tbilisi road
2010-2012
593.9
31.
Rehabilitation of 36th km of Tbilisi road and implementation of relevant safe measures
2010
350.8
32.
Restoration of 14th km of Tbilisi road
2011
771.6
33.
Rehabilitation of roads and regulation building of bridge on 12th km of Tetritskaro-Dageti-Topani road
2011
104.8
34.
Rehabilitation of carriageway of Tsiteli khidi border crossing point
2011
323.1
35.
Rehabilitation of Tbilisi(Pantiani)-Manglisi damaged road
2011
355.5
36.
Restoration works of riv. Mtkvari bed in Gardabani district damaged by natural disaster
2011
1,437.1
37.
Installation of light signals on Tbilisi-Tsiteli Khidi road
2011
72.7
38.
Rehabilitation of bridge on riv. Mtkvari on 47th km of Tbilisi road
2012
1,139.0
39.
Rehabilitation of 17th-26th km section of Didi Dmanisi-Dmanisi-Gomareti-Bediani road
2014

40.
Rehabilitation of 7th-11th km section of Shulaveri-Tsiteli Khidi road
2013
2,646.9
41.
Rehabilitation of 27th-32th km section of Didi Dmanisi-Dmanisi-Gomareti-Bediani road
2013
2,110.0
42.
Rehabilitation of bridge of Shulaveri-Tsiteli Khidi road
2013
448.2
43.
Rehabilitation of 22nd-33rd km section of Tbilisi road
2013-2014

44.
Rehabilitation of 22nd-33rd km section of Tbilisi road
2013
3,277.4
45.
Shore Protection works on riv. Mtkvari near high voltage pole in Rustavi
2013
229.8
46.
Rehabilitation of 46th-51st km section of Tbilisi-Tsiteli Khidi road
2014

47.
Rehabilitation of stone bridge on Tbilisi(Pantiani)-Manglisi road
2014-2015

48.
Rehabilitation railway viaduct on 22th km+300 of Tbilisi-Bakurtsikhe-Lagodekhi road
2014-2015

49.
Rehabilitation railway viaduct on 22th km+370 of Tbilisi-Bakurtsikhe-Lagodekhi road
2014-2015

50.
Shore protection works on riv. Mtkvari in Rustavi
2014

51.
Rehabilitation of 4th-16th km section of Tsereteli-Mirzoevka-Muganlo-Kesalo road
2014-2015

52.
Rehabilitation of 1st-7th km section of Bolnisi-Sioni Monastery-Tsugrugasheni road
2014-2015

53.
Periodic repairing of Khashuri-Vale road
2008-2009
796.9
54.
Rehabilitation of Khertvisi-Vardzia-Turkish border road
2008-2009
3,021.9
55.
Rehabilitation of Adigeni-Ude-Arali road
2008-2009
3,708.6
56.
Rehabilitation of Akhaltsikhe-Ninotsminda road
2009-2012
4,227.8
57.
Rehabilitation of 18th-39th km of Akhaltsikhe-Ninotsminda road (remaining works)
2009-2010
9,729.4
58.
Rehabilitation of Batumi(Angisa)-Akhaltsikhe road
2009-2010
2,628.8
59.
Rehabilitation of Bakuriani circle road
2010
1,608.4
60.
Periodic repairing of Khashuri-Vale-Turkish border road sections
2008-2009
2,713.5
61.
Rehabilitation of 37th, 38th, 39th, 41st, 42nd, 44th km sections of Khashuri-Vale-Turkish border road
2008-2009
2,976.7
62.
Prevention measures on 19th km of Khashuri-Akhaltsikhe-Vale road
2009
147.5
63.
Rehabilitation of bridge of Akhaltsikhe-Ninotsminda-Armenian border road
2010
718.2
64.
Rehabilitation of 135th-136th km section od Batumi-Akhaltsikhe road
2010
1,684.8
65.
Rehabilitation of bridge and regulation walls of Khashuri-Akhaltsikhe-Vale road
2010
47.6
66.
Rehabilitation of road in Bakuriani
2010-2012
2,268.3
67.
Rehabilitation works on 91st-96th km section of Khashuri-Akhaltsikhe-Vale-Turkish border road
2010-2011
2,366.5
68.
Rehabilitation of Minadze-Uraveli road
2011
4,878.8
69.
Rehabilitation of Rabat fortress road in Akhaltsikhe
2012
1,441.2
70.
Works on improvement of organization of traffic in Akhaltsikhe
2012
1,027.8
71.
Rehabilitation of damaged section of Akhaltsikhe-Ninotsminda road
2012
1,900.0
72.
Rehabilitation of 36th, 37th, 55th, 59th, 68th sections of Khashuri-Akhaltsikhe-Vale road
2012
2,011.5
73.
Rehabilitation of 65th, 67th sections of Khashuri-Akhaltsikhe-Vale road
2012
1,342.3
74.
Rehabilitation works on Akhaltsikhe-Greli-Safara Monastery road
2012
264.4
75.
Rehabilitation of 71st-73rd sections of Khashuri-Akhaltsikhe-Vale road
2013
1,294.7
76.
Rehabilitation of 68th-69th sections of Akhaltsikhe-Ninotsminda road
2013
721.3
77.
Rehabilitation of Zarzma-Adigeni section of Batumi-Akhaltsikhe road
2013
2,450.5
78.
Restoration of damaged part of Batumi-Akhaltsikhe road
2013
346.4
79.
Rehabilitation of road of Zarzma Monastery
2013
349,0
80.
Shore protection works on riv. Gujareti in Borjomi Municipality
2013
37,6
81.
Prevention measures on Batumi-Akhaltsikhe road
2013
274,9
82.
Rehabilitation of bridge on Khashuri-Akhaltsikhe-Vale-Turkish border road
2014

83.
Rehabilitation of 11th-12th km section of Khashuri-Akhaltsikhe-Vale road
2014

84.
Rehabilitation of 35th, 40th-41st km section of Khashuri-Akhaltsikhe-Vale road
2014

85.
Rehabilitation of 63rd, 69th-70st km section of Khashuri-Akhaltsikhe-Vale road
2014

86.
Rehabilitation works on 27th km of Khashuri-Akhaltsikhe-Vale road
2014

87.
Construction of bridge on Khashuri-Akhaltsikhe-Vale-Turkish border road
2014

88.
Rehabilitation of 29th km section of Borjomi-Bakuriani-Akhalkalaki road
2014

89.
Rehabilitation of Mlashe-Mokhe-Dertseli road
2014-2015

90.
Rehabilitation of 68th-74th km section of Borjomi-Bakuriani-Akhalkalaki road
2014-2015

91.
Rehabilitation Project of watering system in Marneuli
2011-2012
4,078.9
92.
Rehabilitation of watering system in Marneuli
2014
500.0
93.
Rehabilitation of watering system in Tsalka
2014-2015

Total
109,610.0